Water Network Water Main Renewal Project D&C

Commenced
April 2025
Budget
$1M
Photos
22 photos
Water Network Water Main Renewal Project D&C client

Scope of works

  • Detailed design and construction of the following watermain sections through our Gympie council’s network that have been identified as requiring renewal / upgrade as part of council’s larger water main network renewal program:
  • Inglewood bridge crossing (replace DN100 Cast Iron with DN180 HDPE pipe)
  • Fox Street (replace DN150 Asbestos cement main with DN150 PVC pipe)
  • Excelsior Road (Upgrade existing DN100 main to DN150 PVC pipe)
  • Pengelly’s creek (replace existing section of DN375 DICL main)
  • Pressure testing and commissioning
  • Connection to existing GRC watermain network.