Installation of 2.5 km of DN150 PVC reticulation Sewer Main.
Construction of 54no. Sewer Manholes
Connection of 89no. houses to trunk sewer line. Works involved de-commissioning of on-site treatment systems & hooking each individual resident to the newly installed sewer main.
Liaison with council stakeholders to ensure minimal disruption to residents.