G5 & G5A Sewer Pump Station Bypass Project

Commenced
January 2020
Budget
$0.35M
Photos
17 photos
G5 & G5A Sewer Pump Station Bypass Project client

Scope of works

  • Supply and installation of 480m (DN300-DN150) PVC bypass pipelines.
  • Site fabrication and installation of 8 x DN1200 in-situ sewer manholes.
  • Decommissioning and demolition of pump station structures G5 and G5A.
  • Construction of concrete apron for creek crossing.
  • Implementation of non-destructive hydrovac trenching through tree protection zones.
  • Reinstatement of asphalt pavement for road crossings.