Emerald (QLD)
Emerald Water Supply Upgrade
- Commenced
- July 2018
- Budget
- $0.5M
- Photos
- 21 photos
Scope of works
- Supply & install 1.5km of DN100 uPVC water main.
- Installation and connection of existing water services.
- Implementation of shut‐down plan to mitigate impact of water outages on residents and businesses.
- Connections to existing council water supply infrastructure.
- Pressure testing, chlorination and commissioning of new main.
- Horizontal directional drilling of water main under sensitive structures and main roads.
- Traffic and pedestrian management throughout project. Project located adjacent to both residential lots and busy community bike path.